Published Sunday, July 17, 2005 by G. Jonathan Birinyi | E-mail this post
Last week, Jonathan and I went to see the status of the community kitchen. It is about halfway to completion. The next steps are: Flooring, plastering walls, installing windows and doors and putting up wall pipes to run the electricity through.
As we wait for a response from the WHE committee, Kivulini has agreed to forward the funds for the next steps of constuction.
We will be sending the community contract this week.

Community kitchen in progress

Floor at present-needs cement

Roof-needs repair.